Mountain View approves 119 condos on Maude Avenue under AB 130
Mountain View approved 119 Maude Avenue condos under AB 130. Review demolition, garage and site-management details before the next contractor permit checks.
Mountain View has approved a six-story, 119-condominium development at 855–875 Maude Avenue, giving contractors a newly documented housing project to evaluate beyond the initial proposal stage. The city's Community Development Director approved the project on October 27, 2026. A Notice of Exemption posted October 29 records the city's use of the AB 130 housing exemption under Public Resources Code Section 21080.66. City-filed notice on CEQAnet
The filing identifies Toll Brothers as the applicant. The 1.84-acre redevelopment would replace two commercial buildings with the residential project, a partially underground podium parking garage and related site improvements. Fifteen percent of the homes would be affordable. The entitlement request also includes a vesting tentative map for 119 condominium units and one common lot. Project description and applicant record
Site conditions belong in the estimating review
The project description attached to the filed notice points to specific environmental conditions: compliance with a Site Management Plan/Feasibility Study, regional water board oversight approvals, agreed tribal-consultation requirements and city conditions. Those references matter to contractors evaluating demolition, excavation and material handling. The notice does not give enough detail to price those obligations. Filed notice and attached project description, page 4
The next useful documents are the approved plans and conditions, the applicable site-management requirements, and any grading and building-permit records. They can establish whether the available drawings are developed enough for a meaningful estimate and which requirements apply to a proposed scope.
For teams considering the garage work, questions about excavation limits, shoring, waterproofing and groundwater assumptions should come before pricing. These are due-diligence questions prompted by the below-grade design, not confirmed construction requirements. Residential trades should also verify the current construction system, phasing and procurement approach rather than infer them from the six-story description.
What to check next
- Match subsequent filings to 855–875 Maude Avenue and parcel numbers 160-59-003 and 160-59-004.
- Obtain the October 27 approval, conditions and latest approved plan set.
- Review the referenced site-management and regulatory requirements with the project team before pricing affected work.
- Check demolition, grading and building-permit status separately.
- Verify current bid contacts through an official Toll Brothers channel.
The approval and AB 130 finding establish a concrete milestone. They do not establish mobilization timing, available bid packages or building-permit issuance. The records reviewed here provide no open bid invitation or confirmed construction start. Estimating commitments should follow current plans, permits and a verified procurement path.